Tender Notice Montenegro Hydroelectricity
Reconstruction and Modernisation of Hydro Power Plant Perućica
Tender Award
Dec 20, 2022
- Country Montenegro
- Financing KfW Entwicklungsbank
- Reference Number BMZ201968437/KfW505134
- Subject Reconstruction and Modernisation of Hydro Power Plant Perućica, Phase II
Brief description of the Contract:
Reconstruction and modernization of the power plant Perućica (307 MW)
- Reconstruction and modernization of hydro-mechanical and electrical equipment for units U5 – 38 MW, U6 - 58.5 MW and U7 - 58.5 MW (main equipment to be reconstructed: nozzles with driving servomotors, jet deflectors, turbine governors, turbine inlet valves, unit excitation and electrical braking systems, generator voltage equipment, 110 kV equipment, unit electrical protection systems, unit control systems, unit and step-up transformer monitoring systems);
- Reconstruction and modernization of the system for hydrological and hydraulic measurements on the headrace and tailrace system of the power plant;
- Reconstruction and modernization of the hydro-mechanical and electrical equipment in valve chambers of the plant’s headrace system
- Reconstruction and modernization of the plant level control system which will enable real time control of the power plant, optimal control of water resource within the real time, as well as planning of the power plant operation based on prediction models and analysis of operation in the previous period